Ship Loader Design and Installation - Cape Flattery

Design and installation of new 2500T/Hr ship loader

Located on the eastern side of Cape York, The Cape Flattery Silica sand mine is approximately 240km North of Cairns. In a logistically challenging project, JPR was engaged to design a new 2500T per hour ship loader.

JPR was responsible for the procurement of all electrical equipment for the ship loader and its shipping to Japan for installation by the Japanese machine builder. JPR also managed quality assurance throughout the project, the no load testing and the commissioning of the ship loader in Japan prior to its shipping to site. Once on site, JPR will manage the final assembly and commissioning of machine and site performance testing of the completed system.

Location

Cape Flattery

Client

Cape Flattery Silica Sand Mine

Scope

Design and installation of new 2500T/Hr shiploader

Contract Value

$1.66 Million

Start Date

01/12/2016

Completion Date

01/11/2018

“Well organised, high calibre people – nothing is too much trouble for them. I can’t speak highly enough of JPR.”

Garry Bartholdt, General Manager
Cape Flattery Silica Mine

  • 23

    Project Duration (months)

  • $ 1.66 m

    Contract Value