Mechanical and Electrical Replacement - City of Gold Coast
Mechanical and electrical replacement program: switchboards and pumps
With the City of Gold Coast hosting the 2018 Commonwealth games in April 2018, a renewal of critical infrastructure is a key part of the city’s preparations.
The contract of upgrading /replacing the electrical and mechanical infrastructure of the city’s 40 wastewater pumping stations was awarded to JPR. With a tight delivery timeframe, the project was entrusted to JPR due to the company’s local manufacturing base and extensive expertise in the changeover of live water infrastructure assets.
Location
Gold Coast
Client
City of the Gold Coast, Gold Coast Water
Scope
Replace multiple sewer pumping stations by designing, manufacturing, installing and commissioning the sites in a compressed time frame to support the 2018 Commonwealth Games
Contract Value
$7.5 Million
Start Date
01/11/2016
Completion Date
01/09/2017
JPR completed the first 30 sites commencing with detailed design, manufactured all switchboard components then commissioned all sites in 30 weeks – ahead of schedule and under budget. 10 month Project Duration $7.5m Contract Value
Ahead of schedule and under budget
-
10
Project Duration (months)
-
$ 7.5 m
Contract Value